Construction Update December 2023

We are proud to present the latest chapter of architectural excellence and progress with our December 2023 Construction Update for Sunshine Beach Resort & Residences. This coastal haven, poised on Bangtao Beach, is witnessing remarkable strides in its development.

Building A4:
  • Installation of plumbing and electrical pipelines on the second to fourth floors is 100% complete.
  • Installation of windows on the second to fourth floors is 100% complete.
  • Plastering of internal and external walls is 100% complete.
  • Air conditioning installation is 100% complete.
  • Model rooms are 100% complete.
  • Glass curtain wall in the lobby on the first floor is 100% complete.
  • Stone cave modeling template is 100% complete.
  • Ceiling and GRG framework welding is complete.
  • Marble and stone for the cave have arrived.
  • Hanging wall toilet tanks are 100% complete.
Building A5:
  • Masonry on the first floor is 95% complete.
  • Masonry on the second to fourth floors is 100% complete.
  • Plastering of internal walls on the second to fourth floors is 100% complete.
  • Pre-embedded installation of plumbing and electrical pipelines on the second to fourth floors is 95% complete.
  • Hanging wall toilet tanks are 45% complete.
Building E:
  • The main structure of Building E is 100% complete.
  • Masonry: 100% complete for floors one to five.
  • Pre-embedded installation of plumbing and electrical pipelines: 98% complete for floors one to five.
  • Internal wall plastering: 65% complete for the first and second floors, and 100% complete for the first, and third to fifth floors.
  • Hanging wall toilet tanks are 90% complete.
  • Installation of the freight elevator is 100% complete.
Building D:
  • The main structure of Building D is 100% complete.
  • Masonry: 85% complete for the first floor, and 100% complete for the second to fifth floors.
  • Pre-embedded installation of plumbing and electrical pipelines: 98% complete for floors one to five.
  • Internal wall plastering: 90% complete for the third and fourth floors.
  • Hanging wall toilet tanks are 75% complete.
  • Installation of the freight elevator is 100% complete. 

Building C:
  • The main structure of Building C is 100% complete.
  • Masonry: 100% complete for floors one to five.
  • Pre-embedded installation of plumbing and electrical pipelines: 95% complete for floors one to five.
  • Internal wall plastering: 96% complete for floors one to three and five. 15% complete for the fourth floor.
  • Hanging wall toilet tanks are 65% complete.
  • Installation of the freight elevator is 30% complete. 

Building B:
  • The main structure of Building B is 100% complete.
  • Masonry: 100% complete for floors one to five.
  • Pre-embedded installation of plumbing and electrical pipelines: 95% complete for the first floor, 85% complete for the second floor, and 50% complete for the third floor.
  • Hanging wall toilet tanks are 80% complete.
  • Installation of the freight elevator is 70% complete.
Building A1:
  • The main structure of Building A1 is 100% complete.
  • Masonry is 100% complete.
  • Pre-embedded installation of plumbing and electrical pipelines: 100% complete for floors one to four.
  • Internal wall plastering: 100% complete for floors one to four.
  • Hanging wall toilet tanks are 100% complete.
  • Installation of the freight elevator is 65% complete.
  • Air conditioning installation is 30% complete.
  • Installation of balcony doors and windows is 35%.
Building A2:
  • The main structure of Building A2 is 100% complete.
  • Masonry is 100% complete.
  • Pre-embedded installation of plumbing and electrical pipelines: 100% complete for floors one to four.
  • Internal wall plastering: 100% complete for floors one to four.
  • Hanging wall toilet tanks are 100% complete.
  • Installation of the freight elevator is 25% complete.
  • Air conditioning installation is 10%.
Building A3:
  • The main structure of Building A3 is 100% complete.
  • Masonry is 100% complete.
  • Pre-embedded installation of plumbing and electrical pipelines: 100% complete for floors one to four.
  • Internal wall plastering: 100% complete for floors one to four.
  • Hanging wall toilet tanks are 75% complete.
  • Installation of the freight elevator is 10%.
Perimeter Wall:
  • The rainwater pipes and roads on the north side sections of Buildings A5, D, and E are 100% complete.
  • The perimeter wall on the east side of the river channel is 100% complete.
In the upcoming month, the focus will be on the following construction activities:
  • Continuing the ongoing progress of the construction projects mentioned earlier.
  • Installing aluminum alloy doors and windows for Buildings A1 and E.
  • Commencing the decoration of the lobby and interior ceilings for Building A4.
  • Undertaking interior decoration for the model rooms in Building A5.
  • Finalizing the masonry on the first floor of Building D.
  • Conducting plastering for the walls of Buildings A5, B, C, D, and E.
  • Constructing the foundation beams for the perimeter wall along the river channel.
  • Progressing with the sewage treatment facilities on the east side of Buildings E and C, the construction of the No. 3 water tank on the north side of Building A1, and the water tanks for Buildings C and A3.
  • Advancing the main structure construction for Building G. Initiating the construction of the 10th pool.