Sunshine Beach Resort & Residences Construction Update January 2024

Dive into our exclusive January 2024 construction update! Witness the progress of Sunshine Beach Resort & Residences, a beachfront masterpiece by T.H. Group Phuket. Explore construction milestones, envision your dream villa, and access valuable project insights. Don’t miss this opportunity to secure your piece of paradise in Phuket’s prime location. Luxury awaits. Start your island investment journey today!

Building A4:

Lobby marble floor tiling completed 100%, hole stone installation 20%. Room ceilings completed 60%.

Building A5:

Plumbing and electrical pipes embedded on floors one to four 100%, wall-mounted toilet tanks 65% complete. Model room decoration completed 100%.

Building E:

Internal wall plastering in Building E completed 100%. Wall-mounted toilet tanks completed 100%. Installation of balcony aluminum alloy doors 78% complete.

Building D:

Plumbing and electrical pipe embedding in Building D: Floors one to five 98% complete. Internal wall plastering completed 66%. Wall-mounted toilet tanks completed 85%.

Building C:

Internal wall plastering in Building C: 89% complete. Wall-mounted toilet tanks completed 85%. Installation of freight elevators 90% complete.

Building B:

Plumbing and electrical pipe embedding in Building B: Floors one to three 95% complete, floors four to five 85% complete. Internal wall plastering completed 83%. Wall-mounted toilet tanks completed 90%. Installation of freight elevators 95% complete.

Building A1:

Internal and external wall plastering in Building A1: Completed 100%. Installation of freight elevators 100%, air conditioning installation 100%, pipeline wiring 100% complete. Installation of balcony aluminum alloy doors 82% complete. Room ceilings 5% complete.

Building A2:

Internal wall plastering in Building A2 completed 100%. External wall plastering completed 75%. Installation of freight elevators 85%, air conditioning installation 20% complete.

Building A3:

Internal and external wall plastering in Building A3 completed 100%. Wall-mounted toilet tanks completed 100%, installation of freight elevators 40%

For the next month, the focus will be on:

Continuing the construction progress as mentioned earlier. Installation of aluminum alloy doors and windows for Buildings A1, E, A2, A3, and A5. Lobby renovation for Building A4 and room ceilings for Buildings A1, A2, A3, and A4. Furniture installation for the model rooms in Building A5. Plastering of walls for Buildings A5, B, C, D, and E.

Installation of sewage treatment facilities on the east side of Buildings E and C, as well as Water Tanks 3 for Building C and Water Tanks for A3. Main structure construction for Building G. Construction of Pools 3, 5, 7, and 10.

Key milestones for decoration, installation, and landscape completion:

Hotel Part (A1, A3, A4, B, C) Aluminum alloy doors and windows installation: April 15, 2024 Ceiling installation: May 10, 2024 Wall and floor tile laying: May 10, 2024 Entrance door installation: June 10, 2024 Lighting and bathroom fixture installation: June 30, 2024

Apartments (A2, A5, D, E) Aluminum alloy doors and windows installation: March 25, 2024 Ceiling installation: April 15, 2024 Wall and floor tile laying: May 10, 2024 Entrance door installation: May 25, 2024 Lighting and bathroom fixture installation: June 10, 2024

Main structure of the swimming pool to be completed by March 10, with decoration finished by June 10.

Roadways and perimeter walls to be completed by May 20.

Green landscape to be completed by June 30.

Contact Form