Discover the epitome of opulence in Phuket’s real estate scene as we present the November 2023 construction update for Sunshine Beach Resort & Residences, meticulously crafted by the esteemed T.H. Group Phuket. Immerse yourself in the evolution of our luxurious condotel and premium residences, each development a testament to the commitment of creating an unparalleled living experience.
Building A4
Hydropower Pipeline Installation (2-4 Floors): Completed at 100%.
Windows Installation (2nd to 4th Floors): Currently at 40% completion.
Interior and Exterior Wall Plastering: Successfully completed at 100%.
Air Conditioning Sample Installations: In progress.
Glass Curtain Wall (1st-floor Hall): Successfully completed at 100%.
Stone Cave Molding Template Encapsulation: Accomplished at 100%.
Ceiling GRG Skeleton Welding: Currently underway.
Building A5
Second-floor Masonry: Reached 95% completion.
Masonry (3-4 Floors): Successfully completed at 100%.
Hydropower Pipeline Installation (2-4 Floors): Currently at 95% completion.
Building E
Main Structure: Successfully completed at 100%. Masonry (1-5 Floors):
Currently at 99% completion.
Embedded Hydropower Pipeline Installation (1-3 Floors):
Currently at 95% completion.
Hydropower Pipeline Installation (4th and 5th Floors):
Currently at 90% completion.
Interior Wall Plastering:
First and Second Floors: Currently at 90% completion.
Third Floors: Currently at 93% completion.
Four Floors: Currently at 30% completion.
Building D
Main Structure: Successfully completed at 100%.
Masonry (2nd Floor): Reached 98% completion.
Masonry (3-4 Floors): Successfully completed at 100%.
Masonry (5th Floors): Currently at 99% completion.
Embedded Hydropower Pipeline Installation (2-4 Floors):
Currently at 95% completion.
Interior Wall Plastering (2-4 Floors): Currently at 95% completion.
Interior Wall Plastering:
Four Floors of Slurry Rejection: Currently at 55% completion.
Third Floors: Currently at 80% completion.
Building C
Main Structure: Successfully completed at 100%.
Masonry (1-3 Floors): Currently at 99% completion.
Masonry (4-5 Floors): Currently at 95% completion.
Embedded Hydropower Pipeline Installation:
1st Floor: Currently at 95% completion.
2nd Floor: Currently at 90% completion.
3rd Floor: Currently at 75% completion.
Interior Wall Plastering: 1st Floor:
Currently at 95% completion.
2nd Floor: Currently at 75% completion.
Building B
Main Structure: Successfully completed at 100%.
Masonry: 1st Floor: Currently at 99% completion.
2nd and 3rd Floors: Currently at 97% completion.
4th and 5th Floors: Currently at 92% completion.
Embedded Hydropower Pipeline Installation:
1st Floor: Currently at 95% completion.
2nd Floor: Currently at 85% completion.
3rd Floor: Currently at 50% completion.
Building A1
Main Structure: Successfully completed at 100%.
Masonry: Successfully completed at 100%.
Embedded Hydropower Pipeline Installation:
1st and 2nd Floors: Currently at 100% completion.
3rd Floor: Currently at 95% completion.
Interior Wall Plastering:
1st to 4th Floors: Currently at 100% completion.
1st Floor: Currently at 100% completion.
2nd Floor: Currently at 25% completion.
Building A2
Main Structure: Successfully completed at 100%.
Masonry: Successfully completed at 100%.
Embedded Hydropower Pipeline Installation:
1st to 3rd Floors: Currently at 100% completion.
4th Floor: Currently at 80% completion.
Interior Wall Plastering:
1st to 4th Floors: Currently at 100% completion.
1st and 2nd Floors: Currently at 100% completion.
3rd Floor: Currently at 18% completion.
Building A3
Main Structure: Successfully completed at 100%.
Masonry: Successfully completed at 100%.
Embedded Hydropower Pipeline Installation (1-4 Floors):
Currently at 100% completion.
Interior Wall Plastering:
1st to 4th Floors: Currently at 100% completion.
1st Floor: Currently at 100% completion.
2nd Floor: Currently at 30% completion.
The Wall
Main Structure: Successfully completed at 100%.
Masonry: Successfully completed at 100%.
Embedded Hydropower Pipeline Installation (1-4 Floors):
Currently at 100% completion.
Interior Wall Plastering:
1st to 4th Floors: Currently at 100% completion.
1st Floor: Currently at 100% completion.
2nd Floor: Currently at 30% completion.